Well 6 Ground Storage Tank Rehabilitation
CLIENT City of Pflugerville
LOCATION Pflugerville, TX
PROJECT STATS
COMPLETION DATE
2021
Location
Pflugerville, TX
SERVICES
Water Supply and Treatment
500,000
Gal Ground Storage Tank
1
Month Design Time
PROJECT OVERVIEW
Well 6 is a 500,000-gallon ground storage tank (GST) in Pflugerville, Texas. The tank was taken out of service due to its age and required repair items. Our team worked with the city to design a project to make the necessary repairs improvements to allow the tank to be put into service, help extend the tank’s service life and better serve the Pflugerville community.
SERVICE DETAILS
The tank’s main repair required removing and replacing the tank’s entire roof with a self-supporting dome, which benefited the city by reducing and simplifying future maintenance. The project also consisted of removing and replacing various appurtenances of the tank and blasting and recoating the tank’s interior and exterior.
The project required the design to be completed within a month, including time for the city to review and provide comments on the contract documents. The tank had also been out of service due to its condition, so it was critical the design was completed quickly so the project could go to bid as soon as possible. The project required a design schedule of 28-calendar days to be prepared to advertise the project. Quiddity completed the design phase in 22-calendar days.
Video footage was provided by Heart of Texas Inspection Services.
Associated Project Members
Grady Turner, PE, Senior Project Manager
Water Conveyance and Treatment
Learn More About Grady
Nieves Alfaro, PE, PACP, LACP, MACP, Vice President
Wastewater Collection and Treatment
Learn More About Nieves
Gary Rabalais, PE, Senior Vice President
Water Conveyance and Treatment
Learn more about Gary
Nathan Walton, PE, Construction Services Manager
Water
Learn more about Nathan